News in 2004
January 5, 2004: opening of tunnel connecting
station Museo
(Linea 1)
with box office inside Archaeological Museum has been delayed to April
(see news
- in Italian -
from Il Mattino).
January 9, 2004: The ancient harbour of Neapolis (2nd century after Christ) has been
re-descovered thanks to works for station
Municipio of
Linea 1.
Among many other things, archaeologists have found a 13-metre long boat,
vases coming from Middle East, amphoras filled with oil, wine and perfumes.
The Museum of History of the City should be placed in the station
Municipio.
Article (in Italian) from
La Repubblica on line,
and an
article (in Italian)
from
Il Mattino.
January 11, 2004: ruins of Roman Imperial age buildings are being found
also during works for station
Duomo
(Linea 1)
(see news - in Italian - from
Il Mattino).
January 11, 2004:
Comune di Napoli
asks
Ministry for Infrastructures
direct management for construction of
Centro Direzionale
-
Aeroporto
section of
Linea 1
(see news - in Italian - from
Il Mattino).
January 16, 2004: more and more archaeological discoveries are being made
during excavations for stations
Municipio
and
Duomo
(Linea 1):
Naples vice-Mayor Rocco Papa announces that protected paths are being
considered to allow public visits to working areas
(see news 1
and
news 2
- in Italian -
Il Mattino).
January 21, 2004: Comune di Napoli
approves construction of a pedestrian underpass in
Montesanto
area between
Linea 2
station and that of
Linea 5
and
Linea 7
(see news
- in Italian - from
Il Mattino).
January 21, 2004: Comune di Napoli
approves the preliminary project for
Piscinola
-
Aeroporto
section
(Linea 1).
Area previously occupied by old Alifana line tracks is expected to become
a pedestrian path with gardens and squares
(see news
- in Italian - from
Il Mattino).
February 7, 2004: on March 1st, single ticket fare increases from 77 cents to
1 euro. In return, a wider offer of services and discount for some kinds of
monthly and yearly tickets
(see news
- in Italian -
Il Mattino).
February 24, 2004: station
Duomo
(Linea 1)
will likely be the last one to be completed, due to archaeological
discoveries being constantly made in the area
(see
news 1
and
news 2
- in Italian - from
Il Mattino).
February 24, 2004: start of works to realize station
Mostra
(Linea 6),
and for its underground interconnection to stations of
Linea 2,
Linea 7 and
Linea 8
(see
news
- in Italian - from
Il Mattino).
February 27, 2004: on March 1 ticket and pass fares increase: single ticket
will cost one euro
(see
news
- in Italian - from
Il Mattino).
March 19, 2004: station
Duomo
(Linea 1)
will be built wider than planned, and will contain all
old Greek-Roman objects being found,
among which the whole Gymnasium (the temple of
Neapolitan Olympic Games)
(see
news
- in Italian - from
Il Mattino).
April 11, 2004: 257,000 euros funded to investigate feasibility of
Linea 9.
By end of summer decision will be made whether to build it or to
build a cable-car system instead of it
(see
news
- in Italian - from
Il Mattino).
April 18, 2004:
Linea 6
project slightly modified:
station Martiri replaced by new station
Chiaia - Monte di Dio, with three exits: via Chiaia,
piazza Santa Maria degli Angeli and piazza Santa Caterina.
By end April CIPE is expected to confirm
220 million euro funding
(see
news
- in Italian -
from Il Mattino).
April 21, 2004: portuguese architect Alvaro Siza officially presents to
Comune di Napoli
his project for a new design of
Piazza Municipio:
his proposal also contains design of stations of
Linea 1
and
Linea 6
(see
news
- in Italian - from
Il Mattino).
May 29, 2004: Madonnelle - Botteghelle section of
Linea 3
has been completed.
Now the line is completely in service with 11 stations in 12 kilometres.
Initial frequency is 30 minutes, and transport capacity is about 4000
passengers in rush hours
(see
news #1
- in Italian - from
Il Mattino,
and
news #2
- in Italian - from
ASCA).
June 4, 2004: pedestrian underpass connecting station
Museo
(Linea 1)
and National Archaeological Museum is ready to enter service.
Its description can be found in the
news
- in Italian - from
Il Mattino.
October 7, 2004: new building site for
Linea 6
works is going to be opened in Municipio Square:
car traffic diversions planned
(see
news
- in Italian - from
Il Mattino).
October 21, 2004: CIPE (Interministerial Committee for Economic Programming)
has approved funding for completion of
Linea 6.
First section will enter service in 2009,
and line will be completed in 2011
(see
news
- in Italian - from
Il Mattino).
December 21, 2004: a CIPE preliminary meeting has started procedures for 181.3 million euro
funding to complete
Capodichino -
Centro Direzionale
section of
Linea 1
(see
news
- in Italian - from
Il Mattino).
December 29, 2004: Regione Campania has
funded 17 million euros for
Linea 1.
Among these, 12 will be used to complete
Dante
-
Centro Direzionale section,
2 for restyling of station
Vanvitelli (in which works by artist Mario
Merz will be exposed), and 3 for the new exits and for restyling of station
Scampia-Piscinola
(see
news
- in Italian - from
Il Mattino).
December 30, 2004: good chances to open
Mostra
-
Mergellina
section of
Linea 6
by end 2005 - early 2006.